25 June 2026 • 11 minute read
MACSE 2026: What’s new in Terna’s updated energy storage auction rules
A practical guide to the key regulatory changes for the November 2026 tender
The Italian Ministry of Environment and Energy Security (MASE) has approved an updated version of the MACSE Rules (Disciplina del meccanismo di approvvigionamento di capacità di stoccaggio elettrico), the regulatory framework governing Italy’s energy storage capacity procurement mechanism managed by Terna. The second MACSE auction is scheduled for 24 November 2026, with 16 GWh of storage capacity up for tender. This article highlights the most significant changes compared to the 2024 MACSE Rules that governed the first auction.
Categories of storage systems
Perhaps the most significant structural change is the reorganisation of Article 6 of the MACSE Rules, which now clearly distinguishes between four categories of storage systems, each with dedicated eligibility requirements:
- new systems using reference technologies, ie electrochemical lithium-ion (Article 6.1)
- new systems using non-reference technologies (Article 6.2)
- reconversions (riconversioni) of existing hydroelectric plants (Article 6.3)
- upgrades (potenziamenti) of existing pumped-hydro facilities (new Article 6.4, as the 2024 MACSE Rules didn’t include a dedicated provision for upgrades).
Qualification requirements
The 2026 MACSE Rules expand the information that participants must provide during the qualification process under Article 7.1. In addition to the documentation and data required by the 2024 MACSE Rules, applicants must now disclose the identity of the relevant grid operator; the applicant for the connection request; the connection request reference code (codice di rintracciabilità or codice pratica); and the geographical coordinates of the project site.
Participants also have to indicate the expected date of fulfilment of the construction obligation (obbligo di realizzazione) (new Article 7.1, point VIII).
The 2026 MACSE Rules also introduce a formal distinction between the total technical parameters of a storage system (energy and power capacity) and the portion the participant wishes to qualify for the MACSE auction (Article 7.1, points V and VII), with a view to recognising that storage systems may serve multiple purposes, as a portion of the capacity of a MACSE-awarded project can be reserved for merchant activities, ancillary services contracts or other revenue streams.
Shorter pre-auction guarantee deadline
The deadline for submitting the pre-auction guarantee has been reduced from 40 to 35 days before the auction date (Article 7.2), while the pre-auction guaranteed amount remains calculated as 10% of the qualified capacity multiplied by the reserve premium (Article 40.1, previously Article 34.1).
Algorithm transparency
Terna will now publish the technical specifications of the bid selection algorithm at least 50 days before each auction (Article 10.5).
10% cap on non-reference technologies
With a view to prioritising proven lithium-ion systems, the 2026 MACSE Rules impose an explicit quantitative limit on alternative storage technologies, as capacity from systems using non-reference technologies cannot exceed 10% of the national contingent in any given auction (Article 12.4).
Anti-concentration rules
The 2026 MACSE Rules clarify that capacity contingents are subject to anti-concentration constraints; where all qualified capacity in a given area belongs to a single participant (or to participants within the same corporate group) the minimum contingent for that area is set to zero (Article 12.10, previously Article 11.10).
Partial acceptance and capacity carry-forward
The 2026 MACSE Rules introduce a new mechanism for handling partially accepted bids (Article 19.3-19.9, previously Article 17.3-17.4). If only part of a project’s offered capacity is selected, the participant can either refuse the commitment entirely or, for certain system types, request that the unselected capacity be carried forward to the next auction. If carried forward, the capacity obligations and remuneration will be based on the combined outcome of both procedures, with the premium calculated as a weighted average (Article 19.7).
Pre-auction exclusion phase
The 2026 MACSE Rules now expressly regulate a pre-auction exclusion procedure (Article 10.7, previously Article 10.5), which wasn’t formally addressed with the same level of detail in the 2024 MACSE Rules. Systems can be excluded by Terna at least 20 days before each auction if the qualification process is incomplete, including for missing declarations under Article 7.3 or failure to provide requested integrations under Article 7.4.
Balancing market integration
The conditions for fulfilling the construction obligation (obbligo di realizzazione) have been clarified under Article 21.3 (previously Article 19.1). A storage system will be completed with energy and power capacity at least equal to the committed values; comply with Grid Code technical requirements and functional requirements of the balancing services market (MBR); and be enabled to participate in the balancing services market (MBR). The 2026 MACSE Rules now also distinguish between “individually enabled units” (UAS - Article 21.4) and “nodal virtual enabled units” (UVAN - Article 21.5), with specific qualification requirements for each.
Early completion option
The 2026 MACSE Rules introduce a new regime for the early completion of the construction obligation (adempimento anticipato dell’Obbligo di realizzazione) under Article 29.
This provision directly relates to the new requirement under Article 7.1, point VIII, which requires participants to declare, during the qualification phase, the expected date of fulfilment of the construction obligation. This declaration serves a dual purpose; it enables Terna to monitor project timelines and allows participants to signal their intention to complete early and benefit from the pre-delivery operational flexibility.
If the participant operates the storage system before the delivery period begins under Article 29.1, the start and end dates of the delivery period remain unchanged (Article 29.2). However, participants may also request an early start of the delivery period by submitting a request by 30 September of any calendar year within the planning period. If approved, the delivery period would begin on 1 January of the following year, though in no case earlier than 1 January 2028 (Article 29.3).
Participants electing to bring forward the delivery period must:
- waive the exemptions available during the first calendar year of the delivery period under Article 30.2 (which provide that the participant doesn’t receive the portion of the reserve premium (corrispettivo fisso) attributable to the storage system; is exempt from the availability obligation (obbligo di disponibilità); and is exempt from the variable fee and contribution margin return obligation (obbligo di restituzione del corrispettivo variabile e del margine di contribuzione)); and
- enter into a new implementation agreement (Accordo attuativo) with updated delivery period dates, while keeping the overall duration unchanged (Article 29.4).
Variable fee and contribution margin return mechanism
The 2026 MACSE Rules substantially restructure the regime for the return of revenues generated from balancing market participation, now addressed in separate provisions depending on whether the storage system participates in the MBR through an individually enabled unit (UAS) or a nodal virtual enabled unit (UVAN).
For systems enabled via UAS, the corrispettivo variabile (variable fee) framework is set out in Article 24. The variable fee is calculated based on a formula that considers: the committed capacity; one-twelfth of the reserve premium of the reference technology with the shortest planning period; and a factor of 0.1 (Article 24.9).
The variable fee applies to the difference between committed power and actual quantities offered and accepted on the MBR, with separate calculations for upward (a salire) and downward (a scendere) quantities (Articles 24.3-24.8).
For systems enabled via UVAN, a parallel but distinct framework applies under Article 25, with the variable fee calculated at the aggregate level of the virtual unit and then allocated to individual storage systems based on their share of total committed power within the UVAN (Article 25.10-25.11).
In addition to the variable fee, participants must return 80% of the positive contribution margin (margine di contribuzione) realised from MBR participation and other dispatching services. This obligation is set out in Article 26 for UAS-enabled systems and Article 27 for UVAN-enabled systems. The contribution margin is calculated monthly as the net revenues from accepted upward and downward quantities, plus any other remunerated services, with negative margins carried forward to offset future positive margins (Articles 26.2 and 27.2).
Post-auction guarantee structure
The post-auction guarantee framework has been substantially restructured under Articles 44-47 (previously Articles 38-41), with the guarantee now required to cover both the planning period and the delivery period, differently from the 2024 MACSE Rules.
The guarantee amount is calculated individually for each storage system based on three factors: the committed capacity; the reserve premium of the reference technology with the shortest planning period; and a percentage that varies depending on the phase of the project (Article 44.2). During the planning period, the percentage is 10%.
Once the delivery period begins (or when fewer months remain in the planning period than the number of years in the shortest reference technology planning period multiplied by 12), the percentage increases to 15% multiplied by the number of years in the shortest reference technology planning period (Article 44.2-44.3).
In continuity with the 2024 MACSE Rules, the post-auction guarantees must be provided in one of two forms: a non-interest-bearing cash deposit (deposito cauzionale infruttifero); or an on-demand bank guarantee (fideiussione bancaria a prima richiesta) (Article 45.1).
Participants can present the guarantee as either a single guarantee covering the entire planning period and delivery period; or annual guarantees with a minimum duration until 31 May of the following year (and in any case not less than 12 months), which are tacitly renewed each year throughout the planning period and delivery period unless formally released by Terna (Article 45.2-45.3).
Withdrawal penalty calculation
The 2026 MACSE Rules introduce a more sophisticated withdrawal penalty regime under Article 28. Participants can exercise the right of withdrawal (diritto di recesso) at any time before fulfilling the construction obligation, either in whole or in part, by notifying Terna (Article 28.1-28.2).
The penalty for withdrawal is calculated as the product of the committed capacity for which withdrawal is exercised; the reserve premium (adjusted monthly per Article 32.2); and a time-variable parameter that depends on when the withdrawal occurs (Article 28.4). Such a time-variable parameter represents a change from the simpler flat-rate approach of the 2024 MACSE Rules.
The time-variable parameter operates as follows: if withdrawal occurs when the number of months remaining until the end of the effective planning period (rounded down) is greater than or equal to the number of years in the shortest reference technology planning period multiplied by 12, the parameter is 1.2 (equivalent to 10% of 12 months). If withdrawal occurs when fewer months remain, or during the delivery period, the parameter equals the greater of (x) 12 or (y) the difference between the number of years in the shortest reference technology planning period multiplied by 12, and the number of months (rounded down) remaining until the end of the effective planning period. If withdrawal occurs during the delivery period, the parameter equals the number of years in the shortest reference technology planning period multiplied by 12 (Article 28.4(c)).
In practical terms, this structure incentivises earlier commitment decisions: participants who withdraw early in the planning period face a lower penalty (based on 10%), while those who wait until closer to the delivery period - or withdraw during the delivery period itself - face substantially higher penalties (up to 15% multiplied by the full planning period duration).
Conclusions
The 2026 MACSE Rules represent a refinement of Italy’s energy storage procurement framework, reflecting lessons learned from the first auction held in 2025 and providing greater clarity on system categorisation, enhanced procedural transparency, new flexibility mechanisms for partial acceptance and early completion, and a more detailed economic framework.
The first tender delivered a sobering outcome for the Italian BESS market; after months of anticipation driven by expectations of high IRRs, the auction cleared at prices well below consensus (averaging approximately EUR13,000/MWh). Notably, 70% of the awarded capacity went to the formerly state-owned utility, which leveraged brownfield developments and economies of scale to undercut competitors. The few independent power producers (IPPs) that secured projects did so by pushing assumptions on technology and CAPEX to their limits, accepting razor-thin margins.
This outcome has created significant market tension. According to MASE’s latest report, there are currently 447 BESS-related authorisation proceedings out of 459 total (May 2025 - April 2026), representing approximately 73 GW of potential capacity, of which over 55 GW are still in the permitting process. With over 7 GW of authorised BESS projects now searching for a viable route-to-market, the industry faces a critical choice between the Capacity Market and the next MACSE tender.
The concentration of awards in the first auction, combined with the regulatory refinements in the 2026 MACSE Rules addressing anti-concentration constraints and corporate group disclosure requirements, suggests that regulators are aware of the competitive dynamics at play.
Participants considering the November 2026 auction should note the shortened pre-auction guarantee deadline (now 35 days), the expanded documentation requirements, and perhaps most importantly - the lessons of 2025: in a market dominated by well-capitalised incumbents with brownfield advantages, success may require not only technical excellence but also a realistic assessment of risk-adjusted returns. Early engagement with the qualification process is essential given the competitive pressures and the 16 GWh of capacity available.