29 June 2026 • 21 minute read
New Charge Determination Methodology and Migration Guidelines of grandfathered electricity projects in Mexico: Key considerations for stakeholders
Regulatory context and scope of publications
On June 18, 2026, two regulations were published in the Official Gazette of the Federation that directly affect grandfathered projects in the field of electricity in Mexico, particularly in accordance with the self-supply and cogeneration schemes under the repealed Public Electric Energy Service Law (LSPEE):[1]
The Agreement of the National Energy Commission (CNE) to issue the Methodology for the Determination of the Charge for the Transmission Service (Charge Determination Methodology), applicable to permittees with interconnection contracts and transmission agreements entered into under the LSPEE:[2]
- The Agreement of the Ministry of Energy (SENER) to issue the guidelines for voluntary and expeditious migration of figures to the Electricity Sector Law (LSE) regime of self-supply and cogeneration permits,[3] as outlined in the explanatory note published in the Official Gazette of the Federation on June 26, 2026,[4] which clarifies, with respect to Stage 7 of the schedule, that the registration period for physical assets with “Enabled” status (subsection g) is from April 5 to April 23, 2027 (Migration Guidelines).
- The content of the Charge Determination Methodology and the Migration Guidelines is related. The Charge Determination Methodology redefines the cost of remaining in the grandfathered regime of the LSPEE and the Migration Guidelines establish an expedited pathway for exiting that regime.
The decision of whether to migrate is ultimately an economic and strategic decision that corresponds to each owner, their self-supply partners or associated establishments, and their funders, based on the analysis of their specific project.
This paper is not intended to replace that analysis. Its purpose is to identify the regulatory, contractual and operational factors that must be considered in order to make an informed decision or conduct the corresponding analysis regarding what needs to be taken into account.
Charge Determination Methodology
Subjective scope: The Charge Determination Methodology applies to any person holding a permit granted under the LSPEE who has an interconnection contract and transmission agreement entered into under that same law, regardless of the generation technology. This is relevant because the previous methodology (RES/066/2010 and its amendment RES/194/2010, referred to in the Charge Determination Methodology) was limited to plants with renewable energy sources or efficient cogeneration. The new methodology expands the scope of obligated subjects.
Replacement of the fixed charge with one linked to the market: The Charge Determination Methodology replaces the fixed-charge scheme known as “postage stamping” with a methodology under which charges[5] are determined based on the amounts that National Center for Energy Control (CENACE) settles with the Federal Electricity Commission (CFE) as a supplier[6] in the Wholesale Electricity Market (MEM).
The applicable formula is as follows, the transmission service charge to be charged to the permittee:[7] (CSTI) = the settlement amount for public transmission service (ISPTEEI) + the amount per public distribution service (ISPDEE) + the amount per operation of CENACE (ISOCENACE) + the amount for related services not included in the MEM (ISCnMEM).
Under this methodology, each project will see a different result depending on its capacity, transmission mode, voltage level, and dispatch pattern. There is no fixed or general percentage increase applicable to all projects. Charges cease to be fixed administrative rates and instead depend on dynamic conditions in the wholesale market.
Reporting and billing obligations: The supplier must invoice the permittees monthly for charges resulting from the Charge Determination Methodology and collect them in accordance with the existing interconnection contracts and transmission agreements. It must also submit a monthly report of the charges to the CNE within ten business days after the end of the reported month. The CNE may review and adjust the Charge Determination Methodology at any time, either ex officio or at the proposal of the supplier.
Transitional regime: The window of protection and its conditions
The Charge Determination Methodology goes into effect on October 19, 2026. From that date, all administrative provisions and previous resolutions that regulated transmission charges for LSPEE permit holders with an interconnection contract and transmission agreement are null and void. All contractual references to previous transmission methodologies are understood to be made under the new Charge Determination Methodology.
Transitory exemption window: The Third Transitory of the CNE Agreement establishes that the new Charge Determination Methodology does not apply – from October 19, 2026 to October 6, 2028 – to permittees who simultaneously meet two conditions:
- Contractual term: The permittees’ interconnection contracts and transmission agreements are effective after October 6, 2028.
- Initiation of the migration procedure: The permittees register their expressions of interest and submit their migration applications in accordance with the Migration Guidelines, within the established deadlines.
During this period of protection, permit holders continue to operate in accordance with their current regulations and pay transmission charges in accordance with the above methodology. This is not a default window – it requires action in time. Those who do not submit their expressions of interest in accordance with the Migration Guidelines before September 18, 2026 are subject to the new Charge Determination Methodology as of October 19, 2026.
Grounds for termination of the exemption: The Fourth Transitory of the CNE Agreement establishes that the exemption window ceases early when the permittee: 1) does not conclude all the stages of the migration procedure, 2) obtains “enabled” status in the physical asset registry, or 3) initiates operations in the MEM. In any of these cases, the permittee must pay in accordance with the new Charge Determination Methodology as of the next billing period following the respective notification.
This means that the waiver does not guarantee that permittees will remain under the old methodology until 2028: If the migration is completed sooner, the charges under the new Charge Determination Methodology take effect immediately. The exemption period is the maximum time available, not the guaranteed time.
Voluntary migration procedure
Character and scope: The Migration Guidelines regulate the expedited procedure for the migration of self-supply and cogeneration permits granted under the LSPEE, associated with plants with a capacity equal to or greater than 0.7 megawatts (MWs) (grandfathered figures) and part of interconnection contracts in accordance with the grandfathered figures (grandfathered contracts).
Migration is voluntary. The grandfathered figures that do not migrate continue until the end of their original validity, subject to the framework of the LSPEE and the new Charge Determination Methodology.
Migration is total and final: The granting of a new permit under the LSE implies the renunciation and termination of the grandfathered permit. The conclusion of the procedure implies the irreversible early termination of the grandfathered contracts and related agreements.
Figures of destiny: Grandfathered figures can be migrated to any of the following generation modalities provided for in the LSE:
- Isolated self-consumption: The plant allocates the energy exclusively to its own consumption needs; it does not require representation by a market participant in “generating” mode.
- Interconnected self-consumption: The plant can be interconnected to the National Transmission Network or General Distribution Networks and allocate the energy to one or more self-consumption users; it can contemplate the delivery of surpluses to the electricity system.
- Generation for the MEM: The holder must migrate all the capacity associated with the grandfathered figure; the plant participates in the MEM directly or through a market participant, complying with the Market Rules and the technical and commercial requirements (measurement, dispatch, accreditation, and financial guarantees, among others).
All three figures can comprise the cogeneration modality. End users may independently choose to migrate to “Qualified Supply” or “Basic Supply.”
Migration modalities: The Migration Guidelines establish six modalities that adapt the process to the characteristics of each project:
- Power Plant Migration
- Joint Migration of Power Plant and Load Points to the MEM
- Migration of End Users as Qualified Users (demand greater than or equal to one MW, individual or aggregate)
- Migration of End Users to Basic Supply
- Joint Migration of Power Plant and local loads to interconnected self-consumption
- Joint Migration of Power Plant and local loads to isolated self-consumption
One-stop shop and integrated file: The procedure is processed exclusively through the Migration Window, an inter-institutional digital platform that integrates a single file accessible to all the Responsible Institutions (Ministry of Energy, CNE, CENACE, CFE, and subsidiaries). The Responsible Institutions may not require additional information, procedures, or payments to those provided for in the Migration Guidelines, except in duly justified cases.
Calendar: The procedure comprises up to nine stages with non-extendable dates. Inactivity at any stage will be understood as a withdrawal:
- June 19–September 18, 2026: Registration of expression of interest
- September 21–October 16, 2026: Submission of the migration application
- October 19, 2026–February 12, 2027: Measurement functionality review
- October 19 to December 24, 2026: Review, single prevention, and admission or disposal
- December 28, 2026–February 12, 2027: CNE resolution and granting of the permit under the LSE
- February 15–March 5, 2027: Pre-registration of physical assets
- February 15, 2027–August 15, 2028: Compliance with technical conditions (“Dispatchable” status and minimum tests in operation)
- August 16–October 6, 2028: Execution of new contracts and early termination of grandfathered contracts
- October 6, 2028: Modification of the status to “Enabled” and start of operation in the MEM or under the corresponding self-consumption scheme
Benefits of the expedited procedure: For those who participate in the procedure within the established deadlines, the Migration Guidelines may provide favorable conditions compared to an ordinary procedure. They do not apply the criteria of binding planning for new plants; new interconnection studies, reinforcement works, or associated payments are not required (provided that there is a grandfathered contract and authorized capacity and parameters are respected). For plants in operation, the new permit may have the remaining term of the grandfathered contract plus up to 15 additional years – not to exceed 30 years in total, subject to the Modernization Program approved by the CNE.
Restrictions during the procedure: It is expressly forbidden to increase the installed capacity during the procedure. Technical modifications are not permitted, except for those necessary to meet measurement requirements, obtain “Dispatchable” status, perform minimum testing in operation, or execute the approved Modernization Program. The installation of storage systems is optional and only applicable to renewable energy plants, without increasing installed capacity.
Technical measurement requirements: The Migration Guidelines impose the accreditation of Minimum Required Measurement Functionality: a five-minute measurement, a communication system in continuous operation, and instrument transformers when applicable. For plants and load points with demand equal to or greater than one MW, the full requirements of Measurement Systems of the Market Rules must be met. The minimum operating tests include voltage range, reactive power capacity, Volts/Hertz limiter, frequency range, primary frequency control, and power quality. The tests must be carried out within a maximum period of 30 continuous working days.
Analysis factors by type of project
The decision to migrate or remain under the grandfathered regime will depend on the specific circumstances of each project and may be preceded by an analysis of various factors, including economic and risk-related considerations. The following are the factors that, according to the published regulations, determine the relative desirability of each alternative.
Projects with long-term contractual validity and relevant transmission charges: For projects with grandfathered contracts effective after October 6, 2028, the new Charge Determination Methodology may have a cumulative economic impact over the remaining years of the project's life. The determining factor is the difference between the current charge under the grandfathered transfer agreement and the estimated charge under the CSTi formula, applied to the specific conditions of the project. The elements to be quantified include contracted capacity, voltage level, dispatch pattern, and energy effectively ported.
Projects with a short-term contractual term or close to expiration: For projects with grandfathered contracts expiring before October 6, 2028, the transitional exemption window may not be achievable on its own terms. For these projects, the question is not whether to migrate within the expedited procedure, but whether the project has technical, commercial, and financial viability under any of the LSE target figures at the time of its expiry. The analysis should focus on the target figure most compatible with the commercial structure of the project and on whether the technical state of the plant allows the operational requirements of the new regime to be met.
Projects with long-term commercial contracts with offtakers: The migration does not only affect the permit and the interconnection contract: It can modify the cost structure that underlies supply contracts with self-supplied partners or facilities associated with cogeneration. The factors to consider include: 1) whether the supply contract allows variations in transmission charges to be passed on to the offtaker, 2) whether there is a change in law clause that covers the impact of the new Charge Determination Methodology, 3) whether the chosen destination figure (self-consumption, MEM) is compatible with the structure of the existing commercial relationship, and 4) whether the offtaker has an interest or capacity to migrate in a coordinated manner as a qualified user.
Projects with current project financing: For funded projects, migration involves the termination of the grandfathered permit and the issuance of a new one, as well as the replacement of the grandfathered contracts with the corresponding contracts and agreements under the LSE – which may trigger provisions of the respective financing documentation. Items that typically require prior review or consent include: obligations not to do that restrict termination or substitution of project permits or contracts; definitions of “Material Permit” or “Project Contract”; provisions on adverse material change events; clauses that restrict modifications to the structure of the project without the consent of the creditor; and assumptions of the financial model that incorporate the transmission charge as a fixed data. Coordination with creditors should be initiated before the expression of interest is registered, not after.
Projects in early stages or without a defined commercial operation date: The Migration Guidelines distinguish the treatment applicable to plants in operation and to plants that have not yet entered into operation. For the latter, the validity of the permit granted may not exceed 25 years (compared to the maximum 30 years for plants in operation with a modernization program). In addition, the migration procedure guarantees the continuity of activities during its processing only if there is a grandfathered contract in force. These projects are encouraged to evaluate the status of progress of works reported and the deadlines to conclude the migration procedure before October 6, 2028.
Potential immediate actions: Reference table
Regardless of the decision taken by each holder regarding migration, below are certain activities and dates to consider in light of the dates provided in the Migration Guidelines to carry out the corresponding migration:
| Potential action | Term |
|---|---|
| Register an expression of interest at the Migration Window (if migration is chosen) | No later than September 18, 2026 |
| Quantify the economic impact of the new Charge Determination Methodology against the current charge of the grandfathered agreement | Before September 18, 2026 |
| Review change in law and force majeure clauses in commercial contracts with offtakers | Before October 19, 2026 |
| Submit a formal migration application | September 21 to October 16, 2026 |
| Coordinate with creditors: Obtain necessary authorizations, consents, or waivers | Before submitting a migration application |
The foregoing is without prejudice to the consideration of bringing the appropriate defense proceedings.
The deadline of September 18, 2026 for the registration of the expression of interest is the key date of the procedure. Once expired, access to the expedited procedure is closed and the new Charge Determination Methodology is applicable from October 19, 2026 without the possibility of temporary protection.
The Migration Guidelines establish that holders of grandfathered figures for the import or export of electricity under the LSPEE may voluntarily request to migrate to the LSE figures in terms of the Migration Guidelines.
In this case, the holder of the grandfathered figure of export of electricity may request to migrate the permit and, where appropriate – after the granting of the power generation permit in terms of the LSE as a result of the migration procedure – request an export authorization in accordance with the LSE Regulations from the Ministry of Energy.
This document is for informational purposes only and does not constitute formal legal advice or opinion. For comments, please contact any member of the DLA Piper México, S.C. team.
[1]Capitalized terms not defined herein have the meanings ascribed to them in the LSE, the Charge Determination Methodology, and the Migration Guidelines, as applicable. Acronyms referred to are cited in Spanish.
[2] Agreement of the National Energy Commission issuing the methodology for determining the charge corresponding to the electricity transmission service provided by the supplier to permittees with electric power generation plants, which have an interconnection contract and agreement for the electricity transmission service entered into under the Public Electric Energy Service Law. Available here.
[3] Agreement issuing the guidelines for the voluntary and expeditious migration of self-sufficiency and cogeneration of electricity to the figures provided for in the Electricity Sector Law. Available here.
[4] Explanatory Note to the Agreement of the Ministry of Energy to issue the guidelines for voluntary and expeditious migration of figures to the Electricity Sector Law. Available here
[5] Methodology for Determining Charges, Article 2, section I (Charge: Amount resulting from the sum of the amounts determined by CENACE derived from the Market Settlement by the Public Service for the Transmission of Electric Power, the Public Service for the Distribution of Electric Energy, the operation service of CENACE and the SCnMEM).
[6] Methodology for Determining Charges, Article 2, Section X (Supplier: State Public Company, Federal Electricity Commission).
[7] Methodology for Determining Charges, Article 2, section VII (Permittee: Person holding a permit granted under the terms of the Public Electric Energy Service Law who has an interconnection contract and Transmission Agreement entered into under the aforementioned law).