18 September 2026 • 9 minute read

Spain launches its new capacity market: key regulatory aspects, auction design and opportunities for the energy sector

On 17 September 2026, Order TED/966/2026 of 15 September (the Order) was published in the Official State Gazette (Boletín Oficial del Estado). It establishes a new capacity market in the Spanish peninsular electricity system. The Order entered into force on 18 September 2026.

 

REGULATORY CONTEXT

From an EU law perspective, this mechanism is grounded in Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019, on the internal market for electricity, which sets out the principles and requirements applicable to the implementation of capacity mechanisms by member states.

Pursuant to that Regulation, the Spanish Government notified the European Commission in November 2023 of its Implementation Plan for such mechanisms. As a result, the European Commission authorized the mechanism in May 2026 as compatible State aid under the Clean Industrial State Aid Framework (CISAF), with a maximum allocation of EUR9,000 million for the period 2026–2036 (approximately EUR900 million per year), subject to the outcome of the auctions.

 

KEY ASPECTS OF THE NEW CAPACITY MARKET

Purpose and nature of the mechanism

The Order establishes a capacity market in the Spanish peninsular electricity system, setting out the requirements for participation as a capacity service provider, the conditions for service delivery, the regulation of auction procedures, and the applicable remuneration and financing regime.

The capacity service is defined as a firm capacity availability service provided by capacity service providers to address potential supply concerns identified in adequacy assessments. The allocation of such capacity service is carried out through the competitive tender procedure established in the Order.

Who can participate?

The Order identifies the following entities as eligible to participate in the capacity market:

  • electricity producers
  • owners of storage facilities
  • final electricity consumers
  • entities providing demand aggregation services, including electricity retailers
  • entities providing generation and storage aggregation services

All these participants must be accredited by the system operator to participate in the auctions (in accordance with the procedure set out in Article 13 of the Order), for which they must meet the various legal, technical, and financial requirements applicable to the holder and the characteristics of each facility, as provided in Article 11. They also have to formally adhere to the regulatory framework established for auction participation within the deadlines set out in the relevant auction call notice (resolución de convocatoria).

What auction modalities are envisaged?

The Order provides for three auction modalities, the volume and frequency of which will depend on demand forecasts and firm capacity needs identified through long-term adequacy assessments, which evaluate the risk of adequacy shortfalls over various time horizons:

Main auction: as a general rule, with a lead time of up to five years between the auction date and the start of service delivery. The delivery period must include at least one year in which an adequacy concern has been identified. Delivery periods vary by participant type:

  • Existing generation and storage facilities: 12 months. Facilities holding an operating license (autorización de explotación) before the auction call notice will be deemed existing.
  • New investments in generation and storage: up to 15 years, intended to reflect a period equivalent to half of the useful life of the relevant reference technology.
  • Demand-side facilities: between 1 and 10 years, with the participant choosing the applicable delivery period within that range.
  • Generation and storage aggregations: may only be formed with facilities with individual firm capacity of less than 1 MW and that share the same status (existing or new investment). For existing facilities, the delivery period is one year; for new investments, the shortest period applicable to the component technologies.

On an exceptional basis, the future auction call notice may establish a capacity quota for new investment entry (which may be declared confidential), with a lead time of up to nine years (as opposed to the general maximum of five years) between service allocation and the start of delivery.

Adjustment auction: associated with a 12-month service delivery period, beginning no later than 12 months after the auction is held. Open exclusively to facilities in service before the auction call notice date, and only for the firm capacity corresponding to modules in service. Designed to address short-term adequacy situations not covered by the main auction.

Transitional auction: from the date the Order enters into force until the start of the first delivery period resulting from the main auction, transitional auctions will be held to ensure electricity demand coverage. As a general rule, they will have the same characteristics as main auctions, with the following exceptions:

  • A transitional auction will be held for each calendar year of the period between the entry into force of the Order and the start of the first delivery period resulting from the main auction.
  • Each transitional auction will include an annual service delivery period.
  • Transitional auctions can be held simultaneously.
  • The definition of the required firm capacity curve may include a maximum price different from that established for main capacity auctions.

What is the auction and award procedure?

Auctions will be resolved through a sealed-bid method with a pay-as-bid payment mechanism. The product auctioned is firm capacity (MW) and the bid variable is the price (EUR/firm MW per year, with no decimals). Bid blocks have a minimum size of 1 MW of firm capacity per facility.

Bids will be ranked from lowest to highest price and selected up to the intersection point with the required firm capacity curve, which will be prepared by Red Eléctrica de España (REE) on the basis of the adequacy assessments and definitively set in the auction call notice, following a proposal by the National Commission on Markets and Competition (Comisión Nacional de los Mercados y la Competencia – CNMC).

A maximum price for the required firm capacity curve may be set (which may be confidential) and, additionally, for main auctions, a confidential reserve floor price applicable to existing generation and storage facilities.

As a safeguard for effective competition, the following may be established: a minimum percentage of bid volume received relative to contracted firm capacity, with the possibility of reducing the awarded volume if the percentage is not met; and a maximum percentage of firm capacity awarded to a single company or corporate group.

The awarded price and firm capacity will not be subject to indexation or adjustment.

What does the creation of a secondary market entail?

Capacity service providers can assign or transfer the rights and obligations associated with capacity service delivery, provided that the assignee meets the legal, technical, financial, and capacity requirements that were imposed on auction participants. The assignment or transfer must take place either through a change of ownership of the facility or through an assignment of a provider’s rights and obligations in favour of one or more different facilities or aggregations.

The system operator has to request the assignment or transfer.

What happens if successful bidders don’t comply?

Capacity service providers have to comply with the obligations set out in the Order. The system operator will verify compliance with the obligations. And it can conduct tests at least once a year to verify the availability of the firm capacity of the facilities. If a facility fails a test, the system operator can conduct up to three successive tests, and it can impose the loss of one monthly or quarterly payment, with a 20% surcharge in both cases. Following the third failed test, the facility will be disqualified from providing capacity services.

The CNMC will inspect service delivery conditions, actual availability, and settlement statements issued by REE, and can rule on irregularities and determine the applicable amounts.

A notable innovation? Possible introduction of a maximum CO₂ emissions threshold

One of the most noteworthy aspects of the design of the future auctions is the possibility that the call notice for main auctions can establish, on an exceptional basis, a maximum CO₂-equivalent emissions threshold that successful bidders can’t exceed.

This is an ex ante selection criterion that allows environmental considerations to be incorporated into the award process itself. Unlike the 550 gCO₂/kWh emissions limit applicable as a participation requirement for certain existing facilities, this threshold would operate as an award criterion capable of influencing the final selection of successful bids. Applying this criterion and identifying emitting technologies and determining their emission factors has to be specified in the relevant auction call notice.

 

NEXT STEPS

The Secretary of State for Energy (Secretaría de Estado de Energía) will issue the call for auctions (transitional and main) through a Resolution. Each draft call notice must be submitted to public consultation and to the CNMC for a report, which must be issued within a maximum period of 20 business days.

Once the call notice is published, the period for filing accreditation applications will last a minimum of one month, and the deadline for submission of such applications will be set at least six weeks before the auction date.

The call notice must define: the required firm capacity curve, the firmness coefficients (de-rating factors), the flexibility threshold, the maximum price and, where applicable, the reserve floor price, the delivery periods by reference technology, the Capacity Market Auction Rules, the unit investment values by reference technology, and the new investment hybridization threshold.

The approval, by resolution of the Secretary of State for Energy, of the capacity service operating procedure (procedimiento de operación) is pending. This procedure must set out, at a minimum:

  • the technical, documentary, and operational participation requirements
  • the provider accreditation procedure
  • provider obligations
  • compliance verification and testing framework
  • service settlement
  • service financing
  • the methodology for the calculation of firmness coefficients (de-rating factors) by reference technology
 
FINAL REFLECTION

The primary immediate value of the mechanism lies, in all likelihood, in the medium-term certainty it can provide to lenders, since the possibility of entering into contracts of up to 15 years for new investments provides a regulated revenue horizon that might prove decisive for the financial structuring of battery energy storage system (BESS) projects.

However, the Order merely establishes the general framework of the mechanism, without yet setting its definitive economic parameters. The resulting remuneration will be determined through the corresponding auctions, by means of bids expressed in EUR/firm MW per year under a pay-as-bid system. For the time being, the date of the first auction call has not been announced.

The Order lays the foundations for a mechanism that’s both necessary and long-awaited. Its actual effectiveness will depend largely on the speed with which the still-pending regulatory developments are approved (including the operating procedure, the firmness coefficients, and the auction call notices) and whether the final auction design provides sufficiently attractive economic signals to mobilize the required investment.