30 September 2026 • 13 minute read
Federal Electricity Commission issues new procurement regime provisions and abstention policies in Mexico: Key changes
On August 19, 2026,the Federal Electricity Commission (Comisión Federal de Electricidad, or CFE) published in the Federal Official Gazette (Diario Oficial de la Federación, or DOF) the General Provisions on Procurement, Leasing, Contracting of Services, and Execution of Works of the Federal Electricity Commission (Disposiciones Generales en materia de adquisiciones, arrendamientos, contratación de servicios y ejecución de obras de la Comisión Federal de Electricidad, or the Procurement Provisions).
Issued by the CFE’s Board of Directors through Resolution CA-CFE-058/2026, dated July 13, 2026, the Procurement Provisions entered into force on August 20, 2026 in compliance with Article 81 of the Public State-Owned Enterprise Federal Electricity Commission Law (Ley de la Empresa Pública del Estado, Comisión Federal de Electricidad, or CFE Law).
The Procurement Provisions repeal the General Provisions on Procurement, Leasing, Contracting of Services, and Execution of Works of the Federal Electricity Commission and its Productive Subsidiary Companies (Disposiciones Generales en Materia de Adquisiciones, Arrendamientos, Contratación de Servicios y Ejecución de Obras de la Comisión Federal de Electricidad y sus Empresas Productivas Subsidiarias), published in the DOF on June 23, 2015, together with their various amendments.
On September 18, 2026, the CFE also published in the DOF the Policies Regulating the Circumstances in which the Federal Electricity Commission Shall Refrain from Considering Offers or Entering into Contracts on Procurement, Leasing, Contracting of Services, and Execution of Works (Políticas que regulan los supuestos en que la Comisión Federal de Electricidad se abstendrá de considerar ofertas o celebrar contratos en materia de adquisiciones, arrendamientos, contratación de servicios y ejecución de obras, or the Abstention Policies).
The Abstention Policies, which entered into force on September 19, 2026, establish the procedure and criteria for determining the impediments contemplated in the Procurement Provisions and repeal the prior policies (of the same name) published in the DOF on December 22, 2022, together with their amendments.
In this alert, we summarize the most relevant changes and aspects of both instruments.
Procurement Provisions
Legal nature and scope of application: The Procurement Provisions reflect the legal nature of the CFE as a public state-owned enterprise. Their scope of application is limited exclusively to the CFE and its procurements within national territory.
The Procurement Provisions shall not apply, among others, to:
- Procurements carried out by CFE’s affiliate companies;
- Procurements carried out by the CFE with its affiliate companies;
- Procurements carried out by the CFE with public entities under the purview of the Ministry of Energy (Secretaría de Energía), the Ministry of Navy (Secretaría de Marina), the Ministry of National Defense (Secretaría de la Defensa Nacional), the Ministry of Economy (Secretaría de Economía), or the Digital Transformation and Telecommunications Agency (Agencia de Transformación Digital y Telecomunicaciones), which shall be governed by common law; and
- Procurements that do not generate a payment obligation for the CFE.
Sustainability: Sustainability is one of the guiding principles of the procurement procedures, pursuant to Article 81, Section III of the CFE Law and Provision 3. This principle may result in environmental, social, and governance requirements or evaluation factors within the bidding specifications; accordingly, it is advisable for contractors and suppliers to anticipate their review when preparing offers.
Electronic Procurement System: Procurement procedures shall be conducted, as a general rule, through the Electronic Procurement System (Sistema Electrónico de Contrataciones, or SEC) using electronic identification means. While the SEC is being implemented, procedures shall be carried out through the Procurement Microsite. In-person procedures shall require prior authorization from the Central Contracting Area, except for certain direct awards expressly excluded.
Types of procedures: The CFE maintains four types of procurement procedures: 1) open tender, 2) simplified open tender, 3) restricted invitation, and 4) direct award. These procedures shall continue to be of a national character, an international character under treaty coverage, or an open international character.
Counteroffers: Solely in matters of procurement, leasing, and services, the Procurement Provisions incorporate a new counteroffer stage in open tenders, simplified open tenders, and restricted invitations that cannot be formalized for reasons attributable to the winning bidder – provided that the bidding specifications contemplate it. This stage applies when: 1) the offers exceed the Maximum Procurement Price (the maximum amount resulting from the analysis of market conditions research, at which the CFE would consider the award of a contract feasible), or 2) there is a tie among offers. As a general rule, counteroffers must include a minimum discount of one percent from the Maximum Procurement Price or improve the originally offered price.
Procurement mechanisms: The Procurement Provisions provide for differentiated mechanisms depending on the type of procurement involved. In matters involving procurement, leasing, and services, the mechanisms contemplated under the prior regime are maintained: 1) consolidation, 2) procurement for subsequent fiscal years, 3) on-demand procurement, 4) multiyear procurement, 5) negotiation, 6) joint offer, 7) base discount price, 8) prices subject to adjustment, 9) auctions, 10) subcontracting, and 11) simultaneous supply. Additionally, a new mechanism called “procurement by limits” is incorporated.
Procurement by limits is applicable to services whose scope, volume of work, or specifications cannot be determined in advance. For its implementation, the head of the requesting area must provide a written justification of the circumstances preventing the definition of such elements, incorporating such justification into the market conditions research and the file of the corresponding procedure.
Likewise, the inputs required for the provision of the service may not consist of goods that must enter CFE’s warehouses or be incorporated into its fixed assets. The maximum contract amount shall correspond to the allocated budget and may be increased in accordance with the Procurement Provisions; however, no minimum amount shall be established. Consequently, participants shall assume the uncertainty regarding the volume actually required and must structure their proposals on the basis of unit prices, without any guarantee of demand.
Legal nature: Consistent with the prior regime, the acts within the procurement procedure – up to the moment of the award ruling and all acts tending toward the execution of the contract – are of an administrative nature. Once the contract is executed, the contract and all acts arising therefrom are of a private nature and are governed by applicable commercial or common law.
Amendments to goods and services contracts: Contracts for the procurement or leasing of goods and the provision of services may be increased by up to 50 percent of their total amount, provided that the original contract items, prices, and conditions are maintained, pursuant to legally grounded and explicit reasons issued by the requesting area.
This adjustment represents a material change compared to the prior regime. Although the 50-percent limit and the obligation to maintain the original contract items, prices, and conditions are preserved, the new Procurement Provisions no longer expressly require that amendments continue to represent the most advantageous conditions for the CFE. Instead, it suffices for the requesting area to issue legally grounded and explicit reasons justifying the amendment. For suppliers, this change eliminates a material benchmark and could broaden the CFE’s margin of discretion in authorizing contractual amendments.
Amendments to works contracts: For works contracts at unit prices and mixed contracts, increases in additional work quantities must be formalized through an amendment agreement (convenio modificatorio) provided that 1) there is no substantial variation to the original project and 2) 30 percent of the contract amount is not exceeded. On the other hand, lump-sum works contracts, turnkey lump-sum contracts, or the lump-sum portion of mixed contracts do not admit amendments in amount or term, nor are they subject to cost adjustments.
The Procurement Provisions expressly establish that a substantial variation is one that modifies the main characteristics of the contracted works or the object of the corresponding contract, which shall require a new procurement procedure.
Subcontracting: As with the prior regime, subcontracting requires express authorization in the bidding specifications and the prior consent of the CFE regarding the technical and financial capacity of the subcontractors. The cumulative amount of subcontracting may not exceed 49 percent of the total contract amount.
Assignment of rights: The assignment of rights and obligations is not permitted, except for the assignment of collection rights, which require the prior consent of the contract administrator. Such consent must be granted within a maximum period of five business days; failure to respond within such period shall be deemed a refusal to grant it. Likewise, as with the prior regime, the CFE may authorize or instruct the assignment when circumstances attributable to the supplier jeopardize the performance of the contract.
Administrative rescission: The Procurement Provisions establish a rescission procedure similar to that provided for under the prior regime. The CFE may rescind contracts without the need for a judicial or arbitral resolution in the event of a breach of the corresponding contract, through: 1) written notification of the commencement of the rescission procedure; 2) the granting of a period of 15 business days for the corresponding contractor to assert its rights; and 3) an additional period of 15 business days for the CFE to issue the corresponding resolution.
The CFE may opt not to rescind when the rescission would cause greater harm. In such case, it may grant an additional period to cure the corresponding breach, without prejudice to the application of contractual penalties or the payment of damages arising from such breach.
Social witnesses: The Committee of the Board of Directors shall determine the thresholds above which open tenders must include a social witness, who shall participate as an observer with the right to speak from the issuance of the call for tenders through the award decision. Unlike the prior regime, which contemplated differentiated requirements for individuals and legal entities, the new Procurement Provisions eliminate the category of legal entities as social witnesses and unify the requirements under an individual profile, with the sole exception of nongovernmental nonprofit organizations. Social witnesses shall be selected by the social witness subcommittee from among the persons listed in the corresponding registry. Additionally, the possibility of exempting their participation is incorporated when the procedure contains information classified as reserved.
Reconsideration recourse: The new Procurement Provisions broadened the prior regulation’s scope – under which the recourse was available exclusively against the award decision – to also include the determination declaring a tender or a restricted invitation wholly or partially void. This may open an additional defense against decisions that conclude the procedure without an award. The recourse must be filed before the collegiate body provided for in the CFE’s Organic Bylaws (Estatuto Orgánico de CFE), within five business days following the notification of the award decision or of the corresponding determination.
Dispute resolution: For disputes arising from the interpretation or performance of contracts, as with the prior regime, the parties may agree on alternative dispute resolution mechanisms in accordance with the rules approved by the Board of Directors.
Abstention Policies
The Abstention Policies are intended to establish the criteria and the procedure that the CFE’s contracting areas must follow to establish the impediment grounds provided for in the Procurement Provisions. Among the most relevant grounds that shall require the CFE to refrain from considering offers or entering into contracts are the following:
- Conflicts of interest with the CFE or its affiliate companies;
- Debarments from engaging in commerce, practicing a profession, or holding public office;
- Outstanding breaches under contracts entered into with the CFE, or prior rescission of contracts due to causes attributable to the supplier or contractor;
- Improper obtaining of privileged information;
- Submission of multiple offers by persons under common control;
- Failure to formalize awarded contracts due to causes attributable to the bidder;
- Submission of false information; and
- Declaration of commercial insolvency proceedings (concurso mercantil).
The Abstention Policies broaden certain of the aforementioned impediment grounds. The most relevant is that regarding conflicts of interest, for which a new establishment criterion is incorporated when:
- The bidder has interests adverse to those of the CFE that obstruct the fulfillment of CFE’s purpose, as said purpose is of public interest pursuant to the Electricity Sector Law; or
- Such interests cause harm to the public interest arising from legal, technical, or other strategies implemented under contracts entered into between both parties.
This expansion is particularly relevant, as it introduces an impediment criterion based on harm to the public electricity interest that had no precedent under the prior policies.
The Abstention Policies also establish differentiated periods depending on the contract amount. For procurement, leasing, and services, such periods range from three months for amounts up to MXN510,000 to 24 months for amounts exceeding MXN250 million. For works and related services, the periods range from three months for amounts up to MXN10 million to 36 months for amounts exceeding MXN1 billion. In all cases, the period is computed from the notification of the corresponding determination.
Unlike the prior regulation, the Abstention Policies provide that a bidder, supplier, or contractor may be subject to more than one impediment determination. The responsible areas must be notified of each determination for their corresponding registration. In such cases, the abstention periods shall be computed concurrently; however, the change of status in the registry shall only proceed once the last of the abstention periods arising from the applicable determinations has concluded.
The Abstention Policies contemplate a specific procedure for determining the occurrence of impediment grounds, which includes: 1) notification to the bidder, supplier, or contractor; 2) a period of five business days for the party to submit any arguments or evidence it deems pertinent in defense of its rights and, where applicable, submit evidence; and 3) the issuance of a legally grounded and reasoned determination by the competent area within a maximum period of 15 business days. The Abstention Policies also provide for justified exceptions, which may be authorized when indispensable due to the absence of alternative goods or services, when there is only one possible offeror, in cases of patents or exclusive rights, or in situations of “acts of God” or force majeure.
For more information, please contact the authors.