28 September 2026 • 39 minute read

Draft Royal Decree on Sustainability and Digital Sovereignty Requirements for Data Centres

The Government submitted for public consultation the Draft Royal Decree (the Draft Royal Decree), which sets out the energy sustainability, environmental and digital sovereignty requirements applicable to data centres, in implementation of the First Additional Provision of Royal Decree-Law 7/2026 of 20 March, approving the Comprehensive Plan for Responding to the Crisis in the Middle East (RD-L 7/2026).

 

REGULATORY CONTEXT

The Draft Royal Decree is set against a backdrop of strong growth in demand for data centre capacity in Spain. As Royal Decree-Law 7/2026 itself points out, the access and connection permits already granted far exceed the sector’s development forecasts, which has led the legislator to promote specific regulation of this type of infrastructure.

In this context, the Draft Royal Decree centres on three main pillars: (i) the energy and environmental sustainability of data centres, and their contribution to the energy transition through the integration of new renewable generation and other efficiency measures; (ii) the strengthening of European digital sovereignty, reducing strategic dependencies and reinforcing the protection of data and digital services; and (iii) the incorporation into Spanish law of the energy efficiency reporting obligations set out in European legislation.

 

STATUS OF THE PROCESS

During the public consultation process, the Draft Royal Decree has attracted considerable interest from the stakeholders concerned, with numerous comments and submissions received from sectoral associations, autonomous communities, industry operators and other interested parties. In this Legal Update, we briefly analyse some of the most relevant aspects of the text and certain observations and criticisms raised during the public consultation process.

It should be borne in mind that the text under analysis is still at a preliminary stage. The Council of Ministers has authorised its fast-track processing and, following the conclusion of the public consultation period, the following are still pending: (i) the mandatory reports from the CNMC, (ii) the reports from the various ministries,1 (iii) the report from the Office for Regulatory Coordination and Quality, and (iv) the opinion of the Council of State, prior to its final approval by the Council of Ministers and subsequent publication in the Official State Gazette (BOE).

 
KEY ASPECTS OF THE NEW REGULATORY FRAMEWORK APPLICABLE TO DATA CENTRES

Scope of application

  • The Draft Royal Decree applies to data centres with a power capacity of 1 MW or more, determined by the power capacity stated in the access and connection permits or, where higher, by the power capacity contracted in the third-party network access contract (ATR), including groups of data centres belonging to the same owner and located at the same site, which, when aggregated, reach that threshold.
  • In addition, the reporting and disclosure obligations apply from 500 kW of information technology (IT) capacity.
  • Data centres used exclusively for defence, civil protection and public safety are excluded.

In this context, the practical scope of these requirements is particularly relevant, given the envisaged application threshold (1 MW), which is likely to cover a very significant proportion of the data centres currently in operation or planned in the country. Furthermore, the Draft Royal Decree appears to take as its reference operational frameworks with a high degree of control over the infrastructure and associated technological resources. It will therefore be interesting to analyse how the application of these obligations is structured within different operational frameworks, taking into account the diversity of business models present in the sector.

Establishment of new requirements for the granting of access and connection permits

As indicated, the Draft Royal Decree introduces new regulatory requirements in three main areas: (i) digital sovereignty and resilience; (ii) energy and water efficiency; and (iii) the use of renewable energy. The main new feature of the proposed regime is that compliance with these requirements is established as a necessary precondition for both obtaining and maintaining access and connection permits for data centres. This new link represents a paradigm shift in the access and connection regime, as it makes access to the grid conditional upon compliance with regulatory obligations that go beyond the criteria traditionally associated with the capacity and operation of the electricity system.

  • Submission of responsible declarations with applications for access and connection permits.

In particular, together with the application for access and connection permits, or in the case of applications suspended as a result of the activation of demand access capacity auctions, the data centre operator, or the holder themselves where these roles coincide, must submit to the network operator three responsible declarations relating to:

  • digital sovereignty;2
  • energy efficiency and water efficiency or, where applicable, compliance with the requirements arising from the future European labelling scheme. This declaration must be submitted simultaneously to the Ministry for Ecological Transition and the Demographic Challenge and to the Ministry for Digital Transformation and the Civil Service; and,
  • the use of renewable energy, either through compliance with the minimum renewable generation quota or through the requirements of additionality and hourly correlation.

However, the Draft Royal Decree leaves essential aspects of the responsible declarations scheme to be set out in subsequent regulations, including the applicable forms, the supporting documentation required and the criteria for subsequent monitoring. This lack of specificity creates a degree of legal uncertainty, particularly given that non-compliance with these requirements is directly linked to the granting and maintenance of access and connection permits.

Furthermore, this regime applies not only to future applicants for access and connection permits, but also to projects that already hold such permits and are not yet connected to the grid.3

These data centre projects that already hold permits will have a period of six (6) months to demonstrate compliance with the new requirements. If they fail to do so within this period, the access and connection permits will lapse and the associated financial guarantees will be enforced. As a mitigation measure, the Draft Royal Decree provides for the possibility of waiving the access and connection permit during this same six (6)-month period without forfeiting the guarantees provided.

In this context, the Draft Royal Decree stipulates that applications for access and connection permits which do not demonstrate compliance with these requirements will not be accepted for processing nor will they count for the purposes of triggering demand access capacity auctions in accordance with Article 20 quater of Royal Decree 1183/2020 of 29 December, on access to and connection with electricity transmission and distribution networks (RD 1183/2020). Added to this is a particularly stringent financial regime during the operational phase of data centres, which provides for significant surcharges and even the possible loss of access and connection permits in certain cases of non-compliance.

  • Submission of additional responsible declarations

Furthermore, with regard to digital sovereignty, and prior to the data centre becoming operational, a second responsible declaration must be submitted to the Ministry for Digital Transformation and the Civil Service, certifying effective compliance with the required criteria. For these purposes, the data centre shall be deemed to have become operational at the time the ATR contract is formalised or, if earlier, at the time of the first consumption of electricity. However, although the Draft Royal Decree stipulates that this second responsible declaration must be submitted prior to the data centre becoming operational, it does not specify the deadline or the lead time within which this obligation must be met, which introduces a certain degree of legal uncertainty regarding its practical application.

Furthermore, regarding the efficiency requirement, until a European labelling scheme is in place, operators must submit an annual declaration of compliance by 15 October each year to the MITERD and the Ministry for Digital Transformation and the Civil Service, certifying that the required efficiency levels are being maintained.

 In this regard, the decision to link the access and connection of data centres to compliance with requirements on sustainability, energy efficiency and digital sovereignty has sparked a significant legal debate regarding how this fits within the current legal framework governing access to electricity networks.

In particular, Article 33.2 of Law 24/2013 of 26 December on the Electricity Sector (LSE) stipulates that the refusal of access permits may only be based on a lack of access capacity, without expressly providing for other grounds for rejection or refusal.4

This issue was previously analysed by the CNMC in section 2 of its Report IPN/CNMC/043/25, issued as part of the public consultation and information procedure for the draft Royal Decree on energy efficiency and sustainability of data centres.5 In that report, the CNMC questioned the compatibility of linking some of these requirements to the legal regime for access and connection set out in the LSE.6

However, the matter is far from settled. In fact, the aforementioned report IPN/CNMC/043/25 included a dissenting opinion which argued that there was sufficient authorisation to introduce this type of regulatory condition, based on Articles 33.2 and 33.10 of the LSE.

In this context, it will be particularly important to see the assessment made by the CNMC in the report it issues on this Draft Royal Decree and, in particular, its position regarding the compatibility of this new regime with the LSE. Particular attention should be paid to whether the CNMC provides further clarification on the scope of the government’s authorisation to specify the criteria determining the existence of access capacity or to make the granting of access and connection permits conditional upon compliance with requirements other than those expressly provided for in current legislation.

In addition to this, the only explicit amendment that the Draft Royal Decree introduces to RD 1183/2020, through its First Final Provision, consists of the incorporation of digital sovereignty criteria into demand access capacity auctions, without formally altering the legal grounds for refusing access and connection permits.

 

REQUIREMENTS RELATING TO DIGITAL SOVEREIGNTY, EFFICIENCY AND THE USE OF RENEWABLE ENERGY

Digital sovereignty

When applying for access and connection permits, data centre operators must submit a responsible declaration to the network operator to comply with the applicable requirements.

Furthermore, prior to the data centre becoming operational, they must submit a second responsible declaration to the Ministry for Digital Transformation and the Civil Service certifying effective compliance with these requirements.

In particular, the declarations must cover the following aspects:

  • Requirements relating to establishment within the European Union, the retention of operational data within the territory of the Union, the traceability of access and support services provided from third countries, the supervision of subcontractors, and the adoption of measures to address extraterritorial requirements incompatible with European Union law.
  • Where the data centre hosts information and data subject to the National Security Scheme (ENS), all data must be processed, stored and transferred entirely within the European Union.
    This is a far-reaching requirement which will necessitate a detailed analysis of the technological architectures, international data flows and backup and recovery mechanisms used by operators to verify their compliance with this requirement.
  • The Ministry will carry out a subsequent check on the above requirements, with a minimum period of three months to rectify any non-compliance. Serious non-compliance may result in the loss of access and connection permits.
    However, non-compliance shall not be attributable to the party responsible where it arises from omitted or inaccurate information provided by a customer, supplier or subcontractor, provided that the party responsible can demonstrate that it has taken the contractual, technical and organisational measures set out in the regulation.

In this context, in certain operational models, some of the elements required to demonstrate compliance may depend on third parties or on decisions taken by infrastructure users, which could pose practical challenges in terms of verifying and ensuring ongoing compliance with these obligations.

Furthermore, these requirements may have a particularly significant impact on operators with parent companies based outside the EU, which may, in some cases, need to adapt their operational and contractual structure to meet the new requirements.

Energy and water efficiency

Data centres falling within the scope of the Draft Royal Decree must demonstrate levels of energy and water efficiency equivalent to Class ‘A’ under the future European labelling scheme. Once that scheme is approved, remaining at levels corresponding to Class ‘B’ or lower for two consecutive years will constitute a serious breach and may result in the loss of access and connection permits.

However, until that system comes into force (currently scheduled for August 2027), the Fourth Transitional Provision of the Draft Royal Decree sets out a series of provisional maximum values that must be observed:

  1. Eficiencia energética e hídrica

Los centros de datos incluidos en el ámbito de aplicación del Proyecto de RD deberán acreditar niveles de eficiencia energética e hídrica equivalentes a la clase “A” del futuro sistema europeo de etiquetado. Cuando dicho régimen se apruebe, permanecer en niveles correspondientes a la clase “B” o inferior durante dos años consecutivos constituirá incumplimiento grave y podrá dar lugar a la pérdida de los permisos de acceso y conexión.

No obstante, mientras dicho sistema no resulte aplicable (actualmente previsto para agosto de 2027), la Disposición Transitoria Cuarta del Proyecto de RD establece una serie de valores máximos provisionales que deberán observarse:

Indicador Required threshold
PUE (Power Usage Effectiveness) ≤ 1,15
WUE (Water Usage Effectiveness) ≤ 0,1

 

Under this transitional regime, exceeding a PUE value of 1.15 or a WUE value of 0.1 for two consecutive years constitutes a breach which may result in the loss of access and connection permits.

Furthermore, as previously indicated, the data centre operator must submit the relevant label annually, by 15 October, or, failing that, a responsible declaration certifying compliance with the required efficiency values.

In this regard, the Draft Royal Decree also defers to subsequent regulatory provisions the determination of the format for the responsible declaration, any corrective measures applicable in the event of deviations, and other relevant aspects relating to the measurement and monitoring of the PUE and WUE indicators; this introduces a certain degree of uncertainty regarding the practical scope of these obligations until such provisions are approved.

During the public consultation process, various industry stakeholders have stated that the simultaneous optimisation of the PUE and WUE indicators may pose technical challenges, given that certain cooling solutions favour one of these parameters at the expense of the other.

Consequently, it has been suggested that the practical impact which the joint application of both thresholds might have on different data centre technologies and configurations should be assessed.

Renewable energy

The Draft Royal Decree establishes a dual framework linked to the level of renewable energy penetration in the national electricity mix, inspired by the regime applicable to renewable hydrogen (Delegated Regulation (EU) 2023/1184):7

  • Average share of electricity from renewable sources > 90 per cent: where the average share of renewable generation in the Spanish electricity system has exceeded 90 per cent in year n-2, the requirements for additionality and hourly correlation shall be deemed to have been met; however, the access permit is subject to a maximum number of annual consumption hours, calculated by multiplying the hours in year ‘n’ by the renewable share in year ‘n-2’.

    Exceeding this limit will result in a 65 per cent surcharge, which will increase by 10 percentage points for each additional consecutive year. Once the 90 per cent threshold has been reached, it will continue to be deemed to have been exceeded for the following five calendar years.

During the public consultation process, various operators and sectoral associations have highlighted the practical difficulties that may arise from applying the 90 per cent threshold for the average renewable generation share in the national electricity system, particularly given the current composition of the Spanish electricity mix.

In this context, some commentators have suggested considering replacing this criterion with a threshold linked to decarbonised energy, which would include other generation technologies without direct carbon emissions, on the grounds that this approach could be better aligned with the decarbonisation objectives pursued by the regulation.

As long as the average share of renewable electricity remains below 90 per cent, the requirements regarding additionality and hourly correlation shall apply: until a 90 per cent share of renewable energy is achieved, data centres must demonstrate that at least 80 per cent of their electricity consumption is supported by additional renewable generation. Such generation may come from:

  • self-consumption facilities, located in the immediate vicinity of the centre and developed specifically to supply it, which must not have been commissioned more than 18 months prior to the data centre coming into operation,8
  • or from fixed-term renewable electricity purchase agreements (PPAs) linked to renewable installations situated in Spain, the coming into service of which must not have taken place more than 18 months prior to the data centre becoming operational.

The PPAs must (i) identify the parties; (ii) expressly link the renewable energy facilities to the data centre; (iii) have a minimum term of 10 years; (iv) be recorded in a public deed; and (v) relate to facilities located in Spain.

Coverage based on financial products backed exclusively by guarantees of origin shall not be considered valid. Virtual PPAs entered into by the parent company or another group company shall also not be sufficient, unless they expressly reflect the relationship with the data centre. Supporting documentation must be submitted to the network operator together with the application.

Furthermore, a minimum hourly correlation of 80 per cent is required, such that, in each hour, the available renewable generation covers at least 80 per cent of the consumption occurring during that same period.

Furthermore, any increase in electricity consumption once the centre has commenced operations must be accompanied by additional renewable generation capacity.

During the public consultation process, the above requirements have been the subject of numerous comments from industry stakeholders. In particular:

Appropriateness of the transitional deadlines for signing PPAs: for developers who already hold access and connection permits and are subject to the six-month deadline, signing and finalising PPAs in accordance with the requirements of the regulation may prove difficult within the stipulated timeframe.

Hourly correlation requirement: furthermore, various commentators have highlighted the particularly demanding nature of the 80 per cent hourly correlation requirement. According to these comments, ensuring that at least 80 per cent of consumption is backed by renewable generation in every hour of the year may require advanced energy management and storage strategies, as well as a significant oversizing of the renewable capacity associated with the data centre. In this regard, some stakeholders have warned that applying such a strict hourly criterion from the outset could artificially incentivise the installation of storage systems, not necessarily based on the actual needs of the electricity system, but rather to comply with a particularly rigid regulatory requirement.

In this regard, during the public consultation, various sector stakeholders have proposed replacing the hourly correlation criterion with monthly or annual balancing mechanisms or, alternatively, reducing the minimum coverage percentage required. Other proposals suggest replacing the hourly correlation with aggregated compliance schemes across different time blocks of the year, distinguishing between day and night periods, as well as summer and winter seasons.

It has also been suggested that it should be expressly clarified that renewable energy that is stored and subsequently discharged may count as renewable back-up at the time of its actual consumption, thereby ensuring the technological neutrality of the various storage solutions. It has also been proposed to exclude from the calculation those hours during which there are renewable curtailments or duly documented technical integration constraints, on the understanding that in such situations there is sufficient renewable generation which, for operational reasons, cannot be absorbed by the system.

Additionality: finally, various stakeholders have pointed out that the additionality requirement could limit operators’ freedom to contract, by reducing the number of installations eligible for energy supply. According to these comments, this could create practical difficulties both for the initial contracting and for the eventual replacement of PPAs, particularly when the available generation capacity is already committed.

Furthermore, the requirement for new renewable capacity has been questioned in contexts where there are already surpluses of renewable generation or curtailment during certain time slots, on the grounds that this could force additional investment without an equivalent benefit to the system. In this regard, some respondents have requested that the ‘additionality’ timeframe be extended from 18 to 36 months to allow for the use of renewable projects currently under development or at advanced stages of the approval process. Similarly, it has been proposed that capacity added through repowering and hybridisation projects should count towards compliance with this requirement.

 

NON-COMPLIANCE – SYSTEM OF SURCHARGES AND LOSS OF PERMITS

The Draft Royal Decree establishes a system of surcharges on access tolls and electricity system charges for non-compliance with the aforementioned requirements:

Failure to comply with an obligation Non-compliance threshold

Applicable surcharge on access tolls and charges

Comments
Maximum limit on hours of non-compliance with renewable energy targets

Exceeding the maximum number of hours permitted in acalendar year.

 

Each additional consecutive year of non-compliance.

 

Additional renewable generation < 20 per cent of annual consumption.

 

65%

+10 percentage points per year

500%

Applicable to all bills for the relevant calendar year.

Cumulative increase.

Calculated on the basis of the energy generated by the additional installationsrelativeto annual consumption.

Additionality

≥ 20% and < 40%

≥ 40% and < 60%

≥ 60% and < 80%

Hours of non-compliance < 5 per cent of total hours in the month.

 

400%

300%

100%

10%

 

 

 

Monthly billing.

Hourly correlation

≥ 5% y < 20%

≥ 20%

For each additional consecutive month of non-compliance.

30%

50%

+10 percentage points per month.

Monthly billing.

Monthly billing.

Cumulative increase.

Significant and repeated non-compliance Serious breaches of renewable  energy requirements. Possible loss of access and connection permits.  

 

The loss of permits is reserved for cases of significant and repeated non-compliance, namely where additional renewable generation is less than 60 per cent of annual consumption for five consecutive years, or where the percentage of hours of non-compliance with the hourly correlation is 20 per cent or more during the same period. In all cases, the loss of permits requires a prior notice and a hearing procedure.

 

REPORTING OBLIGATIONS AND ASSOCIATED PUBLICITY REQUIREMENTS

Article 14 of the Draft Royal Decree, in conjunction with its Third Final Provision,9 imposes on data centres with an IT power rating of 500 kW or more the obligation to submit annually, by 15 May, to the Directorate-General for Energy Planning and Coordination the information set out in Annexes I (Information to be reported to the European database) and II (Key measurement indicators) of Delegated Regulation (EU) 2024/1364.

The most significant aspect of the Draft Royal Decree concerns the regime for the publication of this information. In this regard, the information to be submitted by operators, which includes indicators relating to ICT capacity, data traffic, energy consumption and sustainability parameters, will be published by the Government via the website of the Ministry for Ecological Transition and the Demographic Challenge.

Thus, the Draft Royal Decree provides for the individual publication of information which is treated differently in Delegated Regulation (EU) 2024/1364. In particular, Annex IV to the aforementioned Delegated Regulation stipulates that the information available to the public in the European database must be published in aggregate form, both at Member State level and at European Union level, without providing for the individualised disclosure of data relating to each data centre.

In this context, it will be necessary to analyse the compatibility of the disclosure regime set out in the Draft Royal Decree with the applicable European framework, particularly with regard to the scope of the disclosure obligations and the confidentiality safeguards provided for by EU legislation. This issue was already highlighted by the CNMC in section 3 of its Report IPN/CNMC/043/25 in the context of the previous Draft Royal Decree onenergy efficiency and sustainability, which was subject to public consultation inAugust/September 2025, in which it recommended ensuring that information was published in aggregate form, related to past actions, and that the disclosure or exchange of commercially sensitive information between operators was avoided.

In this regard, particular attention should be paid to the fact that the responsibility for identifying information protected by trade secrecy initially lies with the operator itself. This approach could raise certain practical issues regarding the effective protection of strategic or commercially sensitive information, particularly given the high level of technical and operational detail required by Annexes I and II to Delegated Regulation (EU) 2024/1364.

However, several key procedural aspects remain to be developed. In particular, the Draft Royal Decree defers to a future resolution by the Head of the Directorate-General for Energy Planning and Coordination the determination of the procedures for the communication and publication of information; consequently, the operational framework for these obligations has not yet been fully defined.

 
TRANSITIONAL ADAPTATION REGIME

As already noted, the First, Second and Third Additional Provisions of the Draft Royal Decree set out a transitional regime for the application of the new requirements, which has a clearly retroactive dimension in certain cases. Indeed, their scope of application is not limited to new applicants for access and connection permits, but also extends to projects that already hold such permits but which, for the purposes of the regulation, are not yet considered to be connected to the grid:

Scenario Time limit Consequence
Applications currently being processed 3 months Rejection, following a request to rectify deficiencies and a hearing, if the requirements are not met.
Unconnected permits 6 months Loss of permits and enforcement of guarantees.
The Draft Royal Decree does not provide for a rectification and hearing procedure in this case.
Voluntary withdrawal 6 months No enforcement of security10
Digital sovereignty

Deferred until the approvalofa MinisterialOrder implementing the legislation


Energy efficiency August 2027 PUE ≤ 1,15 / WUE ≤ 0,1

 

On the one hand, the application of the new requirements to projects that have already reached advanced stages of development or implementation raises certain issues from the perspective of legal certainty, legitimate expectations and the protection of investments made under the previous regulatory framework.11 These considerations take on particular significance given that the Draft Royal Decree provides for the rejection of applications that do not demonstrate compliance with these requirements, without providing, at least expressly, for mechanisms for a prior hearing or the opportunity to rectify deficiencies, which may significantly increase the onerousness of its effects for the developers concerned.

Furthermore, the Draft provides that, in the event of refusals of access, the relevant access dispute may be brought before the CNMC. However, it expressly states that the CNMC will not review the substantive assessment carried out in relation to the digital sovereignty requirements set out in Article 5, limiting its scrutiny to the formal aspects set out in Article 11.2.

However, this limitation raises certain interpretative doubts. Indeed, Article 11(2) refers to decisions issued in accordance with Articles 5(6) and 6(6) which, once administrative remedies have been exhausted, constitute the basis for the loss of access and connection permits by the network operator and the network owner, respectively. It is therefore unclear whether the exclusion of substantive oversight by the CNMC is intended to apply solely to the digital sovereignty requirements or whether, on the contrary, it should also extend to assessments relating to the energy and water efficiency requirements set out in Article 6 of the Draft Royal Decree.

This difference in treatment could stem from a deliberate decision by the regulator or, alternatively, from an omission in the current wording of the Draft Royal Decree. In this context, the CNMC’s mandatory report will be particularly relevant, both to ascertain its interpretation of the scope of its review powers and to ascertain whether it proposes clarifications or amendments that would resolve this apparent inconsistency.

The definition of the scope of the CNMC’s oversight is of considerable practical importance, insofar as it determines the extent of regulatory supervision and administrative oversight available in relation to decisions taken in application of these new requirements.

The definition of the scope of the CNMC’s oversight is of considerable practical importance, insofar as it determines the extent of regulatory supervision and administrative oversight available in relation to decisions taken in application of these new requirements.

 
FINAL CONSIDERATIONS

In short, the Draft Royal Decree raises regulatory issues of considerable importance for the data centre sector, many of which have already been highlighted during the public consultation period and in previous reports issued by the CNMC.

The progress of the Draft’s legislative process will reveal the extent to which the final text incorporates amendments or clarifications on the issues that have given rise to the most debate, particularly in relation to the access and connection regime (and its retroactive amendment), energy sustainability requirements, the handling of commercially sensitive information, and the alignment of these obligations with the current European and national regulatory framework.


1 Mandatory report from the Technical General Secretariat of the Ministry for Ecological Transition and the Demographic Challenge (MITERD); reports from the Technical General Secretariats of the Ministry for Digital Transformation and the Civil Service and the Ministry of Economy, Trade and Enterprise; a mandatory report from the Ministry of Territorial Policy and Democratic Memory; and a report from the Office for Regulatory Coordination and Quality.
2 The declaration may also include voluntary commitments, such as the reservation of storage or computing capacity for the provision of services to Spanish or European Union companies.
3 For the sake of clarity, a data centre shall only be considered connected once the electrical connection to the grid has been established and the corresponding ATR contract has been formalised.
4 “The granting of an access permit shall be based on compliance with the technical criteria relating to safety, regularity, quality of supply, and the sustainability and economic efficiency of the electricity system, as laid down by regulation by the Government or the National Commission for Markets and Competition, as appropriate. The application of these criteria will determine whether or not access capacity exists. When assessing access capacity, consideration must be given not only to the node to which the facility is connected but also to all nodes influencing the node where the facility is connected, taking into account existing electricity generation and consumption facilities with valid access and connection permits. Similarly, in the aforementioned assessment, the network to be considered shall be the existing or planned transmission network with binding status, or the existing distribution network or that included in investment plans approved by the General State Administration under certain conditions. The access permit shall be granted by the transmission system operator where the point of connection to the grid is on the transmission network, or by the distribution system operator where the point of connection to the grid is on the distribution network. This permit shall set out the specific conditions for use of the network in accordance with the provisions of the aforementioned regulations. In any event, the access permit may only be refused on the grounds of a lack of access capacity. Such a refusal must be justified and must be based on the criteria set out in the first paragraph of this subsection. The right of access may be temporarily restricted. Such a restriction must be justified and must be based on the criteria set out in the regulations referred to in the first paragraph of this section, without prejudice to the provisions of Article 7.”
5 This Draft Royal Decree largely mirrors the content of the aforementioned draft legislation, since the latter was intended to partially transpose Directive (EU) 2023/1791 of the European Parliament and of the Council of 13 September 2023 on energy efficiency and amending Regulation (EU) 2023/955 (recast version) (Directive (EU) 2023/1791). 6 “By Royal Decree of the Council of Ministers, the criteria and procedures that the granting of access and connection must satisfy in order to meet energy policy objectives and the penetration of renewables may be established. To this end, the Government may lay down the criteria under which a party may request network owners and operators to amend the conditions of connection and access permits, including their connection points.”
6 “By Royal Decree of the Council of Ministers, the criteria and procedures that the granting of access and connection must satisfy in order to meet energy policy objectives and the penetration of renewables may be established. To this end, the Government may lay down the criteria under which a party may request network owners and operators to amend the conditions of connection and access permits, including their connection points.”
7 For the sake of clarity, the Impact Analysis Report of the Draft clarifies that “Articles 7, 8 and 9 regulate the requirements relating to renewable energy”, and therefore all energy-related considerations must be interpreted as requirements aimed at ensuring renewable electricity.
8 The data centre shall be deemed to have become operational at the time the ATR contract is concluded or, if earlier, at the time of the first consumption of electricity.
9 “This Royal Decree partially transposes Article 12 of Directive (EU) 2023/1791 into Spanish law.”
10 It is also worth noting that the Draft Royal Decree contains no reference whatsoever to the capacity payment scheme introduced by RD-L 7/2026, nor to the treatment to be given to financial payments for capacity already made by operators prior to its entry into force.
11 Ibid.