9 July 2026 • 5 minute read
Shifting landscapes - Risk allocation and “reasonable time” in Pharos Offshore Group Ltd v Keynvor Morlift Ltd
Offshore and marine installation projects are heavily affected by weather, tides and shifting seabed conditions. The Technology and Construction Court’s July 2025 decision in Pharos Offshore Group Ltd v Keynvor Morlift Ltd is a cautionary tale about what can happen when the time for performance and weather-related downtime risk are not addressed in the contract with sufficient clarity.
Key takeaways
- The Court held that contractual programmes described as “indicative” do not, without clear wording, impose fixed performance deadlines or cap a contractor’s recoverable charges.
- Absent express provisions, the contractor’s obligation will be to perform the relevant services within a “reasonable time”, assessed objectively by reference to the particular offshore conditions and constraints actually encountered.
- The Court rejected the argument that the allocation of risk for adverse weather had shifted to the contractor by implication, emphasising that responsibility for foreseeable offshore risks must be addressed expressly in the contractual terms.
Background
The dispute arose from subsea burial works on the Viking Link project, a major electricity interconnector between the UK and Denmark. Pharos Offshore Group Limited (Pharos) supplied a jet trenching system and personnel to Keynvor Morlift Ltd (KML), which had itself been subcontracted by Prysmian, the main contractor, to perform the embedment works.
The parties’ relationship was governed by a series of purchase orders incorporating KML’s standard terms. Those purchase orders specified daily rates for equipment and personnel in a fixed amount per day for “10 units”. KML asserted that this established a fixed 10-day limit on Pharos’ performance and recoverable charges.
When the project overran - due to equipment issues, weather interruptions, adverse seabed conditions and vessel constraints - Pharos invoiced for the additional time. KML refused to pay, prompting Pharos to issue proceedings. KML counterclaimed, alleging that the jet trenching system and associated equipment failed to meet specification, that Pharos had not completed the works within what it claimed was a fixed 10‑day programme, and that weather‑related downtime risk should fall to Pharos.
Pharos, for its part, disputed that the contract imposed a fixed 10‑day programme or any reallocation of weather risk, and argued that it had performed the works within a reasonable time given the offshore conditions.
Decision
Mr Justice Constable rejected KML’s argument that the purchase orders imposed a fixed 10‑day period for completing the works. He held that the reference to “10 units” merely reflected the parties’ indicative programme- their initial estimate of likely duration: as the purchase order described the programme as "indicative", the “10” was necessarily indicative too, and the daily-rate pricing structure confirmed the duration could vary. Elsewhere in the purchase orders, where the parties intended a cap, they said so expressly—such the GBP81,000 NTE (Not to Exceed) limit for additional equipment—but no such wording applied to the 10‑day figure.
In the absence of clear contractual dates or caps, the Court implied a term requiring Pharos to complete the works within a reasonable time, applying the established principle that obligations without specific timelines are judged by what is reasonable in the circumstances, including the inherent unpredictability of offshore work (weather, tides, operational and logistical constraints). Applying that standard, the judge found a competent contractor would have completed the works by 9 August 2022—later than KML’s asserted 29 July date, but earlier than the actual completion date of 17 August —leaving Pharos responsible for only eight days of delay and otherwise entitled to its outstanding invoices (subject to set‑off).
The Court also rejected KML’s case that weather‑related downtime risk had been transferred to Pharos. Although earlier drafts of the purchase order had included the wording “Plus weather downtime at applicable rates” which was not present in the final versions, there was no evidence of any agreement to remove Pharos’ entitlement to payment during adverse weather. The omission arose because that part of the text was inadvertently overwritten when additional wording was inserted. With no contemporaneous record of a deliberate change— and no reliable witness evidence of a verbal agreement— the original weather‑risk allocation remained. Clear, express drafting is required to shift foreseeable risks such as weather, and none appeared in the revised purchase order.
Significance
This decision offers several important reminders for contractors, developers and suppliers operating in offshore construction and other E&NR construction projects:
- Be precise about time obligations.
Indicative programmes or durations—even when they refer to specific numbers of days—do not create binding deadlines. Unless expressly stated, they remain planning tools only, and performance will be judged against what is reasonable in light of offshore conditions such as weather, tides and seabed mobility. - Risk allocation must be explicit.
Shifting responsibility for foreseeable downtime (such as weather) requires clear drafting. The court rejected the argument that weather risk had moved simply because earlier wording was removed; without a recorded, deliberate variation, the original allocation may stand. - Express dates are essential for liquidated damages.
Liquidated damages will only apply where a delivery or completion date is clearly set out in the contract. Programmes, trackers or assumed mobilisation dates are not enough to trigger LD entitlements. - Document variations.
The failed reliance on an alleged verbal change to the weather‑risk position highlights the need to record any contractual variations in writing. In fast‑moving offshore projects, where parties frequently agree changes on calls or on site, it is vital to record and confirm variations in writing.
Comment
The decision in Pharos v KML underscores the importance of ensuring that contractual clarity extends throughout the supply chain. While primary offshore energy project agreements are often heavily negotiated—frequently using established forms such as FIDIC—lower‑tier arrangements are more commonly concluded under simplified or standard terms. This increases the risk of misalignment on fundamental issues such as time, payment and weather‑related risk, and with it the potential for disputes and unintended liabilities. With climate volatility increasing weather‑driven disruption, clear allocation of foreseeable risks in offshore projects is becoming ever more critical.